Dixie Contractor

Dedicated to the people who make our built environment better and safer. We tell your stories and celebrate your successes.

Register with us and receive industry news and content only available to subscribers.

Subscribe
Contacts

Indianapolis, IN, USA (HQ)

903 E. Ohio St., Indianapolis, IN 46202

Call: (317) 423-2325

info@acppubs.com

Georgia DOT Provides Updates on I-16/I-75 Interchange Improvements Project

MACON-BIBB COUNTY, GA — Contractors for the Georgia Department of Transportation (Georgia DOT) continue construction activities related to the I-16/I-75 Interchange Improvement Project in Macon-Bibb County. The recent activities are listed below.
Ongoing, Long-Term Closures
  • The dedicated right turn lane on the I-16 eastbound off-ramp to Spring Street will remain closed through the spring of 2021.
  • The permanent lane closure on Coliseum Drive/Martin Luther King, Jr. Boulevard southbound between Clinton Street to Riverside Drive; southbound traffic in that area is currently reduced to one lane.
  • The far right lane of I-75 northbound at the Georgia 19/Georgia Avenue exit (exit 164) is closed to traffic for several months.
  • Spring Street's far right lane at the I-16 westbound on-ramp as well as the right-hand on-ramp to I-16 westbound are both closed for several months; the Spring Street on-ramp to I-16 westbound has been relocated to the far left lane.
Phase 2 and 3: I-75 from Hardeman Avenue to I-16 Eastbound
  • Crews continue construction of the Riverside Bridge superstructure over I-75 and the Walnut Street bridge stage two superstructure
  • Continue construction of the new I-75 northbound bridge
  • Continue construction of new I-75 southbound bridge superstructure
  • Continue working on superstructure of the I-16 westbound bridge over the Ocmulgee River
  • Continue construction of two new I-16 westbound to I-75 southbound bridge superstructures
  • Construction of MSE (retaining) walls along I-75 northbound and southbound and at other locations throughout the project continues
  • Construction of concrete sound and visual walls along I-75 northbound and southbound continues
  • Continue demolition of the concrete pavement on the left lane on I-75 southbound from the Riverside Drive bridge to the Hardeman Avenue bridge
  • Continue demolition of the existing pavement on the left lanes of I-75 northbound from Hardeman Avenue to north of the Riverside Bridge
  • Continue grading subgrade and placing gravel mixture in the median of I-75 northbound and southbound from Hardeman Avenue to Riverside Drive and from the new I-16 westbound ramp to the new I-75 southbound ramp
  • Continue installation of light poles on the new I-16 westbound ramp
  • Continue asphalt paving on the new I-16 westbound lanes and ramps to I-75 northbound and southbound
  • Continue concrete paving on the new I-16 westbound to I-75 northbound and southbound lanes
Phase 1: I-16 from the I-16/ I-75 Split to the Martin Luther King Jr. Boulevard Exit
  • Crews continue work on the superstructure for the bridge along I-16 eastbound near Spring Street
  • Construction continues on the superstructure for the new I-16 eastbound bridge over the Ocmulgee River
  • Construction continues on the second stage of the new Martin Luther King Jr. Boulevard bridge over the Ocmulgee River
  • Construction continues on the new I-16 eastbound bridge superstructure over Norfolk Southern Railroad
  • Construction continues on the superstructure for the new I-16 eastbound bridge over Spring Street
  • Construction continues on MSE (retaining) walls along I-16 eastbound between Spring Street and Martin Luther King Jr. Boulevard
  • Grading activities continue on the I-16 eastbound exit ramps to Martin Luther King, Jr. Boulevard and Spring Street
  • Grading activities continue on the entrance ramp to I-16 eastbound from Martin Luther King Jr. Boulevard

The I-16/I-75 Interchange Improvements Project is a $500-million safety and mobility megaproject. With its massive scope to widen and reconstruct I-16, I-75, and their interchange in Macon-Bibb County, this project is being delivered in seven design and construction phases that will continue through 2030. When complete, new CD lanes, additional interstate lanes, new interstate on-and off-ramps, upgrades to 11 bridges, new walls, upgraded drainage systems, etc. will deliver safer and improved mobility for Macon-Bibb County’s local commuters and businesses, regional travelers, and commercial freight from the Georgia southern coast to destinations within the state and throughout the U.S.

Leeboy - Pavers/Asphalt
Your local LeeBoy dealer
Power Equipment Co
Epiroc
Your local Atlas Copco CMT USA dealer
Power Equipment Co